Construction progress of OKINAWA Boutique Residence as of April

24.04.2023 г., from the TASKOV & STOYANOV Team

Construction and installation works on the residential complex OKINAWA Boutique Residence are proceeding according to the pre-planned and approved activity schedules.

The report on the progress of the construction of the OKINAWA building was prepared by the chief engineer of the company "Taskov & Stoyanov" Stefan Nikolov.

During the past 2 months, we managed to finish the following construction and installation works:

• We laid waterproofing on the basement walls up to a height of -2.75m;

• We completed the slab (formwork, reinforcement and concrete) at an elevation of -6.50m, as it has already been de-formulated;

• We installed the second construction crane at the site.

Concrete is currently being poured at an elevation of -2.75m, and from the northern part of the site, this is also the approach to the building, due to the slight unevenness of the terrain. In parallel, the vertical formwork for the elevation +0.15m is being executed.

In the next month (May 2023) it is planned to complete the external walls at the elevation +0.15m and to complete the slab at the elevation +0.15m. We will finish the waterproofing in the foundations. We will begin the implementation of the reverse embankment around the building.

For additional information and to organize a viewing, contact us!

Stay connected with TASKOV & STOYANOV and receive our company news and updates on current and future projects!

If you would like to receive up-to-date information from our company, please follow us on social media or subscribe to our regular monthly newsletter with company news, announcements of new projects, updates on ongoing construction sites, special property offers, and any other relevant information regarding TASKOV & STOYANOV.

You can easily unsubscribe later if you choose to.