Construction progress of OKINAWA Boutique Residence as of October

17.10.2023 г., from the Stonehard Team

Construction progress on Okinawa Boutique Residence is happening at a rapid pace. We present you with up-to-date information on construction and installation activities:

Current information on construction progress has been prepared and summarized by our chief engineer Stefan Nikolov. During the past weeks, we managed to complete the following construction and installation works as follows:

• We finished the formwork, reinforcing concrete works at the +15.90m elevation;

• We have finished the masonry at the +4.10m elevation;

• We are working on the masonry at the +7.05m elevation;

• We have started the formwork of the verticals and the slab at the +18.85m elevation;

• We are working on the waterproofing and back embankment around the site;

• We demolish the slab at the +10.00m elevation.

In the next month, it is planned to complete the entire slab/formwork, concrete and reinforcement/ at the elevation +18.85m and to work on the verticals at the elevation +21.80m. We will start masonry work at an elevation of +10.00m.

For additional information and to organize a viewing, contact us!

Stay connected with TASKOV & STOYANOV and receive our company news and updates on current and future projects!

If you would like to receive up-to-date information from our company, please follow us on social media or subscribe to our regular monthly newsletter with company news, announcements of new projects, updates on ongoing construction sites, special property offers, and any other relevant information regarding TASKOV & STOYANOV.

You can easily unsubscribe later if you choose to.