Construction progress of OKINAWA Boutique Residence as of September

20.09.2023 г., from the Stonehard Team

Construction and assembly works on the residential complex OKINAWA Boutique Residence are proceeding according to the pre-planned and approved activity schedules.  

Current information on construction progress has been prepared and summarized by the chief engineer of the company Taskov & Stoyanov Stefan Nikolov.  

During the past weeks, we managed to complete the following construction and installation works as follows:

• We finished the masonry at the elevation –2.75m;

• We have started the demography of the slab up to an elevation of +7.05m;

• We made the slab/formwork, reinforcement and concrete at an elevation of +10.00m;

• We are working on the waterproofing and back embankment around the site;

• We have started the formwork of the verticals and the slab at the +15.90m elevation.  

In the next month, it is planned to complete the entire slab /formwork, concrete and reinforcement/ at the elevation +18.85m and to work on the vertical elevation +21.80m.

We will start masonry works at an elevation of +4.10m.   For additional information and to organize a viewing, contact us!

Stay connected with TASKOV & STOYANOV and receive our company news and updates on current and future projects!

If you would like to receive up-to-date information from our company, please follow us on social media or subscribe to our regular monthly newsletter with company news, announcements of new projects, updates on ongoing construction sites, special property offers, and any other relevant information regarding TASKOV & STOYANOV.

You can easily unsubscribe later if you choose to.