OKINAWA Boutique Residence construction progress as of April 2024.

12.04.2024 г., from the Stonehard Team

Residential complex OKINAWA Boutique Residence is progressing in its construction, according to the pre-planned and approved activity schedules.

We share with you a video overview and a regular monthly report with the activities carried out in the last month, as well as those planned in the next 30 days.

In recent weeks we have completed a number of construction and installation activities and reached the milestones as described below:

•  We have started the installation of the scaffolding around the building, first completing the western and southern parts, now we are working on the eastern;

•  Plumbing and electrical installations on the elevation  +18.85m have been completed and now we are working at an elevation of +21.80m;

• We are installing the joinery on the 8th floor;

• We have finished plastering the apartments up to and including the 3rd floor and are starting preparations for plastering the bathrooms on the 4th residential floor;

•  We started the construction of the underfloor heating in the apartments. •  We built the gas installation in the basement.  

In the next month, we plan to carry out the following activities:

• Installation of scaffolding on the eastern and northern facades, and starting the construction of the eastern facade;

• We are starting to build the verticals of the gas installation;

• We plan to finish the installation of underfloor heating on the 1st and 2nd residential floors;

• According to the schedule, we should also finish the installation of plumbing and electrical installations at the +24.75m elevation;

• Start with screeds on the first residential floors.

The building has received Act 14 under Art. 181 and to date 78% of the properties have been sold. There are still available for sale one-, two- and three-room apartments at prices from 1430 €/m² without VAT, several shops on the ground floor with prices from 2333 €/m² without VAT, as well as underground parking spaces at prices from €20,833 without VAT.

To organize an inspection or if you need additional information, please contact the responsible consultant Lubin Chakov on phone: +359 882 817 565 or visit the website: www.okinawa.bg

Stay connected with TASKOV & STOYANOV and receive our company news and updates on current and future projects!

If you would like to receive up-to-date information from our company, please follow us on social media or subscribe to our regular monthly newsletter with company news, announcements of new projects, updates on ongoing construction sites, special property offers, and any other relevant information regarding TASKOV & STOYANOV.

You can easily unsubscribe later if you choose to.