Progress in the construction of Comfort Residence – Malinova Dolina II for the month of August 2026.

21.08.2026 г., from the TASKOV & STOYANOV team

In the midst of summer, we are tracking the progress of the construction of Comfort Residence – Malinova Dolina 2 – a modern residential project that is gradually taking on its completed appearance in one of the actively developing areas of Sofia.

The building has received Act 14, and its completion is planned for the end of 2026.

In August, we achieved an important milestone in the construction of Comfort Residence "Malinova Dolina 2" - the building reached the "rough construction" stage, certified in accordance with Article 181 of the Spatial Planning Act.

The project is the work of the established construction and investment company TASKOV & STOYANOV , behind which stand dozens of completed residential projects and hundreds of delivered homes. The implementation of the construction activities has been entrusted to Elite Building Company , and the work on site continues with visible progress on the key stages of the building.

Spread over 4 floors, the building has a ground floor offering apartments with green courtyards, while the top floor offers penthouses with panoramic terraces.

Comfort Residence – Malinova Dolina 2 has a total of 40 apartments, 41 underground parking spaces and 10 above-ground (outdoor) parking spaces. Currently, a limited number of two-bedroom and three-bedroom apartments with functional layouts are offered.

Construction is progressing according to the previously planned and approved linear schedules.

Within the past month, we have also completed a number of construction and installation works:

• We finished the wooden cladding of the visor.

• We finished the North and South facades with plaster and dismantled the scaffolding.

• We are completing the electrical, plumbing, and HVAC installations on the residential floors and continuing work in the basement.

• We finish the terraces with granite tiles.

• We finished the gypsum plaster on the first residential floor.

• We completed the screed on the second and third residential floors.

Next month is coming up:

• Completion of the gypsum plaster on the fourth residential floor and the staircase.

• Installation of the sheet metal on the visor and finishing of the double floor on the top floor.

• Start of laying granite in the common areas.

• Delivery and start of installation of the elevators.

• Dismantling of the remaining scaffolding.

• Implementation of the railings on the terraces.

You can see a video of the construction progress here.

To organize a viewing or if you need additional information, please contact the responsible consultant Lyubin Chakov at tel.: +359 882 817 565 or visit our website.

Stay connected with TASKOV & STOYANOV and receive our company news and updates on current and future projects!

If you would like to receive up-to-date information from our company, please follow us on social media or subscribe to our regular monthly newsletter with company news, announcements of new projects, updates on ongoing construction sites, special property offers, and any other relevant information regarding TASKOV & STOYANOV.

You can easily unsubscribe later if you choose to.